Hybrid Annuity Model (HAM) - Projects
 
S. No. Project Name Client State Length
(km)
Bid Project Cost
(Rs Crore)
Status
1 Delhi Meerut Expressway - Package I
(NH-24)
NHAI Delhi 8.716 841.5 Achieved COD on 28 June 2018; currently in the O&M phase
2 Four-laning of Chutmulpur - Ganeshpur
(NH-72A) & Roorkee - Gagalheri (NH-73)
NHAI Uttar Pradesh and Uttarakhand 53.300 942.00 Under construction
3 Four-laning of Gagalheri - Saharanpur - Yamunanagar (NH-73A) NHAI Uttar Pradesh 51.455 1126.00 Under construction
4 Six-Laning of Aunta - Simaria (NH-31) including Major Bridge over Ganga river NHAI Bihar 8.150 1,161.00 Awaiting Appointed Date
5 Four-laning of Chikhali - Tarsod (NH-6) NHAI Maharashtra 62.700 1,048.10 Awaiting Appointed Date
6 Four-laning of Sattanathapuram - Nagapattinam (NH-45A) NHAI Tamil Nadu 55.755 2,004.51 LOA received in July 2018
 
Build - Operate - Transfer (BOT) - Toll Projects
 
S. No. Project Name Client State Length
(km)
Bid Project Cost
(Rs Crore)
Status
1 Four-laning of Dewas - Bhopal (SH-18) MPRDC Madhya Pradesh 142.600 600.56 In the O&M phase
2 Two-laning of Raisen - Rahatgarh (SH-19) MPRDC Madhya Pradesh 101.100 72.07 In the O&M phase
3 Development of Hoshangabad - Harda - Khandwa road (SH-15) MPRDC Madhya Pradesh 185.600 100.39 Concession Period ended in February 2018; project handed over to MPRDC.
 
 
 
 
 
 